|
|
 
ENERGY NEWS
INDONESIA'S GEOTHERMAL DEVELOPMENT
(Date of Report: February 15, 2002)
Summary
Although Indonesia is among only a handful of countries to develop
geothermal energy, utilization of geothermal potential has proceeded
very slowly and is currently facing difficult challenges and
uncertainty. Over a span of 20 years, Indonesia developed only 787 MW
of geothermal power, or 4 percent of 20,000 MW of geothermal
potential. The early 1990s saw the awarding of eleven contracts for
development of geothermal power plants, with a total committed
capacity of 3,417 MW and original completion dates between 1998 and
2002. As a result of the 1997-1998 financial crisis, the Government
suspended nine conventionally powered Independent Power Projects (IPPs)
and seven geothermal projects. The government is now attempting to
resuscitate the seven contracts but with little progress.
Private sector development of geothermal projects differs from
Independent Power Project (IPPs). While Presidential Directive (PD) 37
of 1992 forms the legal basis for IPPs, PD 45 of 1991 authorized
private sector development of geothermal potential with fundamentally
different terms. PD No. 45/1991 outlines two alternative paths for
geothermal energy development in Indonesia. Under the first, Pertamina
or its joint operation contractors develop and operate the steam field
only, selling the steam to PLN or other parties for electricity
generation. The second alternative allows Pertamina or its contractors
to generate electricity as well as develop and operate the steam
field, with the electricity produced sold to either PLN or other
consumers. A Joint Operating Contract (JOC) governs the contractor's
relationship with Pertamina. PLN buys electricity on the basis of an
Energy Sales Contract (ESC), which is normally denominated in dollars
and obligates PLN to purchase electricity on a take-or-pay basis for a
period of 30 years or more. So far, Joint Operation Contractors of
Pertamina have added 405 MW to geothermal generation capacity. U.S.
companies that are or have been involved in geothermal development
projects in Indonesia include Unocal, Amoseas (a wholly owned
subsidiary of ChevronTexaco), Mid-American (formerly California
Energy), Magma Power Co., Caithness, and Florida Power & Light.
(We provide a detailed project-by-project description and update in
Section VII.)
The new oil and gas law, passed in October 2001, removes geothermal
as an area of regulation, requiring the Indonesian Government to
develop a new legislative basis quickly. A Parliamentary commission is
examining the Indonesian Geothermal Association's December 2001
submission of a draft geothermal law. The law's drafters hope it will
open up new opportunities for geothermal development. In the meantime,
Presidential Decree No. 22/1981, amended by PD No. 45/1991, continues
to regulate geothermal energy exploitation.
PLN understands that geothermal's future development will depend on
its competitiveness against other electricity generation. High capital
costs and the associated electricity tariff required remain core
problems. In addition, unresolved decentralization issues,
uncertainties in security and contracts, and the potential regulatory
changes of a planned geothermal law discourage investment in
geothermal projects. In the long run, Indonesia still presents one of
the world's most attractive geothermal regions, but the Indonesian
Government must develop new approaches to maximize its potential.
end of summary.
For Complete Report (24 pages) please download :
Trends | Reports | Energy | Coal |
Petroleum | Investment
|
|