
|
|
|
YEAR |
2001 |
2002 |
2003 |
2004 |
2005 |
2006 |
|
Installed Capacity |
1232 |
1250 |
1283 |
1283 |
1365 |
1365 |
|
Effective Capacity |
863 |
930 |
981 |
981 |
1019 |
1056 |
|
Peak load |
863 |
929 |
1032 |
1087 |
1187 |
1258 |
|
Reserve Margin |
0 |
1 |
(51) |
(106) |
(168) |
(202) |
IPPs Could be a Big Help
The picture could potentially be much better if Independent Power Projects (IPPs) planned for North Sumatra could be completed. State utility company PLN's projections forecast a greatly improved power situation if the Sarulla and Sibayak geothermal projects were completed in 2004 and the hydropower Asahan 1 and steam-powered Sibolga 2 projects in 2005. Sarulla is capable of adding 300 to 400 MW of which 165 MW is currently included in PLN's system planning. Sibayak's additional generator would add another 30 MW for 195 MW total. In 2005, Sibolga's two 100-MW generators and Asahan's single 90-MW generator would add another 190 MW total.
Table: 9% average demand growth scenario with IPPs (negative
numbers in parentheses):
|
YEAR |
2001 |
2002 |
2003 |
2004 |
2005 |
2006 |
|
Installed Capacity |
1232 |
1250 |
1283 |
1283 |
1365 |
1365 |
|
IPP Power |
0 |
0 |
0 |
195 |
485 |
485 |
|
Effective Capacity |
863 |
930 |
981 |
1176 |
1431 |
1541 |
|
Peak load |
863 |
929 |
1032 |
1079 |
1187 |
1258 |
|
Reserve Margin |
0 |
1 |
(51) |
97 |
244 |
283 |
We stress that PLN provided the above projection for illustrative purposes only and that there is no realistic possibility that the IPPs would be completed according to the above schedule. Presidential decree No. 5/1998 postponed many IPPs or put them under "review," including Sarulla and Asahan I. PLN and a subsidiary of U.S.-based Unocal Corporation are working to resuscitate the Sarulla geothermal project, but substantial progress cannot be made until other IPP issues have been resolved. Pertamina has the legal authority to complete the Sibayak geothermal project, but, like PLN and other state-owned enterprises, it is struggling to find capital for other higher priority needs. The Asahan hydro project and Sibolga are even further from any restart.
Local Government's Response
The local PLN office is struggling to find short-term solutions to add power generation, but has few prospective work-arounds. North Sumatra governor HT Rizal Nurdin made a well-publicized visit on November 29 to Jakarta to discuss North Sumatra's power situation with Energy Minister Purnomo. The governor pressed Purnomo for a modification of the presidential decree postponing completion of Unocal's Sarulla IPP. His visit followed lobbying efforts by other Medan and provincial representatives. The provincial government is already aware of lost investments, most notably a foundry, because of an insufficient electricity supply. North Sumatra has commissioned a Bandung Institute of Technology study to determine an appropriate regional tariff, allowed under new decentralization legislation, which should be completed in mid-2002.
COMMENT
The power shortage problem in Medan and North Sumatra is another lingering effect of Indonesia's economic crisis. The rupiah, once Rp 2,500/$, is now at about Rp 10,000/$, but many prices with large imported inputs, particularly for government or SOE-provided services, have not risen the fourfold needed to compensate for the decline. The average electricity tariff is now about Rp 350/KwH or about 3.5 cent/KwH, still short of the 5-6 cents/KwH electric-production costs of even the most efficient utility in developing countries. New investment to add generating infrastructure will not flow into North Sumatra, no matter how accommodating the provincial government, until the electricity tariff rises sufficiently to provide a reasonable return on investment. The North Sumatra government needs to move quickly to implement a higher regional electricity tariff.
Trends | Reports | Energy | Coal | Petroleum | Investment
U.S.
Embassy Jakarta Home Page
Information
Resource Center | Visa
Information | American
Citizen Services
Top | Feedback | Site Index | Search | Privacy Notice | Bahasa Indonesia
Please contact our Webmaster
with questions and comments.
This page is produced and maintained by American Embassy
Information Resource Center, a state-of-the-art research facility
with access to a wide variety of print and electronic resources.
DISCLAIMER: Links to non-U.S. government Internet sites should not be construed as an endorsement of the views contained therein.